Artifacts found at the construction site for a new roundabout in west Windsor, July 26 2017.  (Photo by Aria Carter)Artifacts found at the construction site for a new roundabout in west Windsor, July 26 2017. (Photo by Aria Carter)
Windsor

Archaeological Dig Could Possibly Delay Roundabout Opening

City engineer Tiffany Prokop insists construction workers are doing the best they can to keep to their tight schedule but admits an archaeological dig at the site has impacted their time table.

"This is a complete unknown, I mean, we just don't know," says Prokop.

The roundabout at Riverside Dr. W and University Ave. W is expected to open September 1.

For the past couple weeks, Jim Molnar with Fisher Archeological Consulting has been working at the site uncovering artifacts unearthed by construction.

"We found pieces for making stone tools. So, these are Indigenous artifacts. They're several hundred up to a couple thousand years old. We've also found pieces of Indigenous pottery," says Molnar.

Some of the artifacts are more recent, however.

"The other things that we're finding are from the late 19th century and the early 20th century. They're from essentially from the time of the Town of Sandwich," he says.

He says the artifacts will be washed and archived.

Molnar says it is possible someone living in west Windsor could find artifacts in their backyard, but they would have to dig down at least a metre, and he does not advise it since archaeology is regulated by the province.

Molnar says so far; the work has gone smoothly. Construction workers have cooperated with the dig.

"The construction company and the City of Windsor have been great partners," he says. "They've been absolutely super about trying to find ways to accommodate what we can do so we don't hinder them."

Work on the new roundabout, which will feature a statue of Chief Tecumseh, started in June.

- With files by University of Windsor intern, Aria Carter.

Read More Local Stories

CEO/CEdO Lisa Demers (right) presents the gavel to Chair John Van Heck, alongside Vice Chair Brenda Rumble. Submitted photo.

Chair and Vice Chair chosen for SCCDSB

The St. Clair Catholic District School Board (SCCDSB) held its inaugural meeting this week, where trustees were sworn in, and a chair and vice-chair were named.

Tiny home build groundbreaking, Tuesday, November 17, 2026. Photo courtesy of Habitat for Humanity Sarnia-Lambton via Facebook.

Big step for tiny home project

Habitat for Humanity Sarnia-Lambton has broken ground on a new tiny-home five-plex at 236 Christina Street South, with construction set to finish by fall 2027.